Jody and Scott continued with the plumbing, running the water line from outside into the DH first floor bathroom and then cutting 4" holes for the toilets on the second floor.
The last block was layed, on the column that will support the inner corner of the slab that the DH water tank will sit on, dedicated to "Kings and Queens" (Audio Adrenaline).
The work of filling the cells with grout and rebar followed close behind, fed by Marc, Wowo and David at the mixer (thanks again Lance!), Jody cutting rebar, and, of course, the bucket brigade!
Meanwhile Bill and Andy started with the central wall in the big bathroom.
Tomorrow the water and vent lines will go in there, and over at the DH we will start forming the bond beam (relax, Gail, the rebar assemblies are already done!).
This team has been so productive that tomorrow afternoon, after the ladies Bible study, we will go up on the mountain. It turns out that no one on this team has been there, despite many of them coming here multiple times.
The Lord continues to bless us in every way, and every day we are seeing more amazing results of every aspect of the ministry He has led us to here, medical, children, construction and outreach. Praise His holy Name!