We had some more rain last night, but not the flood we had Saturday night.
This morning, after devotions, where Mary led the singing, we took up where we
left off Sunday. Bill and Gil and their team decided it would be easier to cut
blocks to make the sloping side wall, which looks great!
Dariel and his team finished the Director house drain field, and then some
of them started helping with the forms for the bond beams,
while Cliff and Jeff were joined by Andy and the rest of the team blocking
in the front wall.
We made an emergency trip to MSC at lunch
time to try and find out what happened to our roofing materials, and discovered
that they are waiting on some of the materials to come in and won't be able to deliver
until Wednesday or Thursday, so we will continue with the Phase One walls and
the Director's house this week. We won't get the roof up this week, but we're
making great progress in other areas. We're flexible!
The ladies had a wonderful time again with the children's VBS after their
regular school in the morning, and didn't get back to us until almost quitting
time!
Please continue to pray for our health and safety, and that we will be open
to where the Lord is leading us.
No comments:
Post a Comment